Adam's approach to each
pool remodeling project is the same: provide timely communication
with the property owner about the sequence of construction,
plan ahead for minimal pool "down time", install
the finest quality materials by highly-skilled pool artisans,
and keep the job site safe and clean. By their very nature,
pool renovations can be messy; however, Adam's crews
are trained to minimize any problems during the course
of construction. Our ultimate objective is your complete
satisfaction.
1. Draining the pool and beginning to remove old coping.
2. Removing the old tile. 3. Saw-cutting
the deck to provide needed spacing from pool beam.
4. Installing"bats" to level the pool, planning
tile and coping installation. 5. Preparing pool "bond
beam" for tile and coping installation. 6. Installing
brick coping.
7. Installing tile. 8. Preparing pool for application
of new surface. 9. Applying the new finish
(plaster or Pebble Tec©.)
10. Hand troweling new finish (plaster or Pebble Tec©.)
11. Completing installation of Pebble Tec©
surface. 12. Final washing of Pebble Tec© surface
(Not required for plaster finish).
click
here to view the Swimming Pool Renovation Process
in more detail.
Here's another example of the Swimming Pool Renovation
Process:
Before
During
After
|